Slamannan Regeneration Fund - Public Realm Proposals

Falkirk Council has allocated a budget of £500,000 for the purpose of delivering projects that will support economic and environmental regeneration in Slamannan.

Following community engagement, undertaken in Summer 2023, the following projects were approved by Falkirk Council on 6 December 2023, for further design and feasibility work:

  • Royal Hotel demolition and creation of green space at this site;
  • Village Clock restoration; and
  • Public Realm Improvements to main parade.

The Royal Hotel demolition project is scheduled to commence in Spring 2024, and complete in Summer 2024.

Preliminary works and tests are ongoing on the Village Clock, and a programme of works will then be confirmed and progressed.

This engagement focusses upon the Public Realm improvements to the main parade and Falkirk Council would like your feedback on the design proposals.

Please review the design proposal documents attached below, and submit your thoughts by clicking on the "add contribution" button on the right hand side of this screen. You can view all contributions below.

Alternatively, come along to the drop-in session on 9 May at Slamanann Community Education Centre, any time between 5pm and 7pm to see plans and talk to a member of the team.

If you would like to speak to a member of the team - please e-mail regeneration@falkirk.gov.uk.

Phases

Phases overview

Design Proposals - Feedback

29 April 2024 23:00 - 28 May 2024 23:00

This engagement phase focuses specifically upon the Public Realm Improvements to the main parade, in Slamannan, and presents design proposals to enhance the area on Bank Street/Main Street/Station Road.

These proposals are now out for 4-week public consultation to gain feedback from Slamannan area residents, local groups and businesses.

If you have any queries relating to the proposals or consultation, please contact regeneration@falkirk.gov.uk.

Alternatively, come along to the following drop-in session at Slamannan Community Education Centre, to look at plans and talk to a member of the team:

  • Thursday 9 May, any time between 5pm and 7pm.

0 contributions

No results found. Please try a different filter or search term.

Filters

Total posts: 0
There are no projects available.

Sorting changed to: Trending

No values available.

Selected zero tag filters.

Upcoming and ongoing events

    0 events have loaded.
    No upcoming or ongoing events are currently scheduled.

    Past events

    1 event has loaded.